TRILITICA FRAME


July 30, 2008

Architecture and Engineering Technical Drawings and Specifications Content according Romanian Practice

Architecture and Engineering Technical Drawings and Specifications Content according Romanian Practice

1.1. Design Theme / Feasibility Study:

1.1.1. Architecture

1.1.1.1. All Stories blueprints

1.1.1.2. Sections Views

1.1.1.3. Exterior Renderings

1.1.1.4. Cost Estimation Sheets

1.1.2. Structure

1.1.2.1. Structural system decision

1.2. Technical Project:

1.2.1. First Page Information

1.2.2. List of architects and Engineers

1.2.3. Architecture:

1.2.3.1. Wrote Parts:

1.2.3.1.1. General Technical Descriptions,

1.2.3.1.2. Costs Estimations Document,

1.2.3.1.3. Global Insulation Coefficient „G”,

1.2.3.1.4. Class and Category of building Importance according Romanian Law,

1.2.3.1.5. Determinative Stages Control Program,

1.2.3.1.6. Technical Descriptions and specifications,

1.2.3.1.7. Estimate of Material Quantities for Architecture and Structural Construction Works.

1.2.3.2. Technical Drawings:

1.2.3.2.1. Plan of Zone 1/2000 scale

1.2.3.2.2. Site Plan 1/500 scale

1.2.3.2.3. Site Plan and Tracing Axes Dimensioning 1/200

1.2.3.2.4. All Stories Blueprints–1/50 scale

1.2.3.2.5. Roof or Roof terrace Plan – 1/50 scale

1.2.3.2.6. Facade Elevations 1/50 scale

1.2.3.2.7. Section Elevations– 1/50 scale

1.2.3.2.8. Execution details – 1/20, 1/10, 1/5 scale

1.2.3.2.9. Doors and Windows Dimensioning Table

1.2.3.2.10. Finishing Tables for each story

1.2.4. Structural Design

1.2.4.1. Wrote Parts:

1.2.4.1.1. Structural Technical Descriptions,

1.2.4.1.2. Specifications

1.2.4.1.3. Reinforcement Extract Tables

1.2.4.1.4. Determinative Stages Control Program,

1.2.4.2. Technical Drawings:

1.2.4.2.1. Foundations and Excavations Plan – 1/50 scale

1.2.4.2.2. Foundations Details - 1/50, 1/20 scale, including Reinforcement Extract Tables

1.2.4.2.3. Floors Encasement plans 1/50 scale

1.2.4.2.4. Steel reinforcement Plans for each floor, including Reinforcement Extract Tables 1/50 scale

1.2.4.2.5. Walls, columns, beams Plans and Elevations, including Reinforcement Details + Reinforcement Extract Tables. 1/50 11/20 scale

1.2.4.2.6. Other reinforcement Details including Reinforcement Extract Tables.

1.2.4.2.7. Other Details

1.2.5. HVAC, Plumbing and Sanitation, Gas and Electricity Design, Fire Extinguish Installations, Fire Alarm Installations, Smoke Exhaust Installations Design:

1.2.5.1. Wrote Parts:

1.2.5.1.1. Technical Descriptions of Installations, including Calculations tables of consuming quantities, Debits etc,

1.2.5.1.2. Specifications,

1.2.5.1.3. Lists of material Quantities

1.2.5.2. Technical Drawings

1.2.5.2.1. All Stories Plans 1/50 scale

1.2.5.2.2. Installations Schemes and Diagrams – 1/50 scale

1.2.5.2.3. General Electricity Panel Scheme

1.2.6. Fire Safety Scenario

1.3. Building Permit Design

The architect extracts the Building Permit Design from the Technical Project.

1.3.1. First Page Information

1.3.2. List of architects and Engineers

1.3.3. Architecture:

1.3.3.1. Wrote Parts:

1.3.3.1.1. General Technical Descriptions,

1.3.3.1.2. Costs Estimations Document,

1.3.3.1.3. Global Insulation Coefficient „G”,

1.3.3.1.4. Class and Category of building Importance according Romanian Law,

1.3.3.1.5. Determinative Stages Control Program,

1.3.3.1.6. Technical Descriptions and specifications,

1.3.3.2. Technical Drawings:

1.3.3.2.1. Plan of Zone 1/2000 scale

1.3.3.2.2. Site Plan 1/500 scale

1.3.3.2.3. Site Plan and Tracing Axes Dimensioning 1/200

1.3.3.2.4. All Stories Blueprints–1/50 scale

1.3.3.2.5. Roof or Roof terrace Plan – 1/50 scale

1.3.3.2.6. Facade Elevations 1/50 scale

1.3.3.2.7. Section Elevations– 1/50 scale

1.3.4. Structural Design

1.3.4.1. Wrote Parts:

1.3.4.1.1. Structural Technical Descriptions,

1.3.4.1.2. Determinative Stages Control Program,

1.3.4.2. Technical Drawings:

1.3.4.2.1. Foundations and Excavations Plan – 1/50 scale

1.3.4.2.2. Foundations Details - 1/50, 1/20 scale, including Reinforcement Extract Tables

1.3.5. HVAC, Plumbing and Sanitation, Gas and Electricity Design, Fire Extinguish Installations, Fire Alarm Installations, Smoke Exhaust Installations Design:

1.3.5.1. Wrote Parts:

1.3.5.1.1. Technical Descriptions of Installations, including Calculations tables of consuming quantities, Debits etc,

1.3.5.2. Technical Drawings

1.3.5.2.1. Installations Schemes and Diagrams – 1/50 scale

1.3.5.2.2. General Electricity Panel Scheme

1.3.5.2.3. Fire Safety Scenario

2. Execution Details

2.1. Adaptive Technical Drawings and Specifications for Finishing’s and Equipments.

3. Technical Support during Execution Phases

3.1. Site Technical Support (included0:

3.1.1. Controls according to Determinative Stages Control Program

3.2. Supplementary Site Technical Support:

3.2.1. Architecture and Engineering for Execution Errors or by Constructor Demand

Final Acceptance Control

No Comments

No comments yet.